This page has answers for the coaching charts exercise
developed by Ron Jeffries and Bill Wake.
Don't peek at this page unless you want to see answers.
The Graphs
| 1. Velocity

This is a very artificial-looking velocity curve. It's hard to believe this
is happening randomly; there must be something going on. Here are some
possibilities; most are bad news.
- The team is purposely controlling its velocity.
- The team is supporting two different projects, and gives each one
emphasis on alternate weeks.
- The team developed the habit of taking it easy on alternate
iterations.
- The team is releasing on alternate iterations, and is spending too
much time preparing for the release (and release isn't counted into
velocity).
- The team is delivering a lot one iteration, but then spending a lot of
the next iteration cleaning up neglected refactorings or fixing bugs.
|
| 2. Lines of Code Address two cases:
Case 1: Velocity is about the same each
iteration
Case 2: Velocity has a curve similar to this one

Case 1: Velocity is about the same each iteration.
This could be a reasonable curve for a team that's doing refactoring:
- when they add features in new areas, the code size increases
- when they add code in existing areas, the code size increases, but more
slowly
- they occasionally get a major insight that lets them drastically reduce
the system's size.
That they're sustaining their velocity even when deleting code is a good
sign.
Case 2: Velocity tracks LOC.
That sounds like a team that earns lots of points when it's adding code, and
few points when it's refactoring to remove code. That
suggests that refactoring is piling up; perhaps the team "crashes" and has to ask for time to clean up so they can make more
progress.
|
| 3. Velocity

The team appears to be generally improving, though there is a lot of
fluctuation. Will the velocity keep trending
upward?
|
4. Acceptance Tests
| Iteration |
Max |
Passing |
| 1 |
E |
A,B,C,D,E |
| 2 |
F |
A,C,E,F |
| 3 |
G |
A,C,D,E,G |
| 4 |
I |
A,C,E,F,G,H,I |
| 5 |
J |
A,C,D,F,G,I,J |
| 6 |
K |
A,C,E,F,G,H,I,J |
| 7 |
K |
A,B,C,D,E,F,G,H,I,J,K |
The most noticeable thing about this chart is its opacity: it doesn't
present it's data in an interesting way. See the later acceptance tests
chart for the same data presented better (and discussion of the data
itself).
|
5. Checkins
| Iteration |
Mon |
Tue |
Wed |
Thu |
Fri |
| 1 |
xxxxx xxx |
xxxx |
xxxxx xxxx |
xxxxx xx |
xxxxx xxx |
| 2 |
xxxxx xxxx |
x |
xxxxx xxxxx xxxxx xx |
xxxxx x |
xxxxx xx |
| 3 |
xxxxx xxx |
xx |
xxxxx xxxxx xx |
xxxxx xxx |
xxxxx x |
| 4 |
xxxxx xxxxx |
xx |
xxxxx xxxx |
xxxxx xxx |
xxxxx xxxxx x |
It's clear that Tuesdays are the day when the least is getting checked in,
and Wednesday seems to try to catch up a little. Is the planning meeting (or
something else) on Tuesdays?
The team is otherwise fairly consistent from day to day and week to week.
How many people are checking in? If it's two or three pairs, then each is
checking in 3 or 4 times a day.
The pattern is clear; does the chart still help the team?
|
| 6. Tasks
This snapshot was taken Wednesday, halfway through the iteration.
|
Tasks |
Story 1
Task A
Task BStory 2
Connect frobbles
Persistence
Darnagle the froogles
Story 3
Lorem ipsit
Quantius maximus |
Story 4
Hopp galoppe
Coniunctirae prillin
Bloddius rankStory 5
Trillin exertes
Postulo mio
Agricanka lama
Needhle pind |
The team is done with half of the tasks, but none of the stories. Are
they cooperating well, or do we have one developer per story? It's hard to
tell if the iteration is in jeopardy - if stories aren't completing for the
same reason, we may have a real problem.
The team is treating all stories as equal priority. I'd definitely push
the team to focus on getting the most important story completed first.
|
7. Acceptance Tests
|
Iteration-> |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
|
|
Test |
|
|
|
|
|
|
|
|
|
A |
P |
P |
P |
P |
P |
P |
P |
A |
|
B |
P |
F |
F |
F |
F |
F |
P |
B |
|
C |
P |
P |
P |
P |
P |
P |
P |
C |
|
D |
P |
F |
P |
F |
P |
F |
P |
D |
|
E |
P |
P |
P |
P |
F |
P |
P |
E |
|
F |
|
P |
F |
P |
P |
P |
P |
F |
|
G |
|
|
P |
P |
P |
P |
P |
G |
|
H |
|
|
|
P |
F |
P |
P |
H |
|
I |
|
|
|
P |
P |
P |
P |
I |
|
J |
|
|
|
|
P |
P |
P |
J |
|
K |
|
|
|
|
|
F |
P |
K |
This is the earlier acceptance test data, recorded in a more
understandable form. Overall, we see that this is not a team that keeps
tests passing once they've passed the first time. (I prefer the ratchet
approach: once it passes, it's kept green.) Note that the team is
adding tests each iteration, but not very many. Only the first and last
iteration had all tests green. What will the next iteration be like? (Did
someone just declare victory on the tests, or are they really all working
right?) Test B is clearly a
problem: it's never passing. Why not? Why hasn't the team addressed this
problem? Test D is also interesting: it's passing on alternate runs.
Sometimes this indicates that a test isn't properly cleaning up after
itself. Or it may be a symptom of other fragility: we fix the problem, but
then the next change breaks it again. In any case, the team needs to work on
this test too. Are these tests being run only once per iteration? Maybe
more frequent reporting would help the team keep them green.
|
| 8. When can we ship? 
The trend line is in a good direction: down. It looks like
the team will be shipping in about two iterations.
The jig upwards at the start of each iteration represents
growth in the number of points remaining, either due to re-estimates or due
to added stories. But notice that this is getting smaller each iteration as
well. It feels like this team is in control.
|
Thanks
Thanks to the attendees of the class Coaching Agile Software Teams
for participating in this exercise.
[Written September, 2004.]
|