Capsule SummaryIn XP, planning at implementation can take place at any time, but an XP project usually has different emphases at different times. Exploration: The team learns about the problem and the technology options for a solution. The programmers estimate the cost of each story. Exploration typically lasts one to four weeks. Result: All important stories are understood (reasonably well) and estimated (in story points). Release Planning: The programmers tell how many story points per iteration they expect to deliver. The customer plans which stories will be in the release, and in approximately what order they should be implemented. Result: A release plan. Iterations: The team implements another group of stories, whichever ones the customer thinks are the most important at that time (and whose cost lets them fit into the iteration). Iterations have a standard size, typically one to three weeks. Result: Working system that the customer can test. Release: The team readies the system for release to a broader group. Releases are typically one to three months apart. Result: System delivered to end users. ImplicationsFrom even the small description above, we can see several implications:
The EstimatesThe programmers work with the customers to make sure both parties agree on the meaning of a story. Then, the programmers give an estimate representing how much effort they believe is involved to deliver that feature. Some teams use relative estimates. A common style is 1 to 3 points; anything bigger than 3, the customer is asked to split the story into smaller stories.) The programmers typically think of a 1 as being, "If this were all I was doing, I could do it in 1 week." Why the relative estimates instead of absolute estimates (e.g., 12 days)? Because people tend to better at relative sizes ("this is about the same work as that"), and they tend to be better at thinking in terms of working time than in estimating their overhead. Other teams use absolute estimates. (This is the approach Kent Beck is currently recommending.) This is typically done in pair-hours (the cost for two people working together for one hour). What if we later find out an estimate is wrong? The team can update their estimates at any time as they learn more. (And yes - if things suddenly get expensive or cheap, it can have a big impact on the release, and the customer may re-assess the overall plan.) The Release PlanOnce every story has an estimate, the programmers declare how much much capacity they think they will average per iteration ("the velocity"). (A reasonable, conservative guess is "1/4 pair-hour per programmer per week.") The customer creates the release plan as a list of features in priority order, grouped into iterations according to the estimate and the velocity. The customer can split any story that doesn’t quite fit (and have the programmers estimate the new stories). For example, assuming a declared velocity of 40 hours per iteration and a team planning to do 3 iterations:
The customer can decide whether the goal for the release is a certain list of features or a certain release date. (Iterations have a fixed duration, but the overall release may or may not be time-boxed.) This plan can (and often should) after each iteration, as the team learns more. The First IterationXP suggests a special goal for the first iteration: it needs to provide a minimal, end-to-end solution involving every major component. (Many components will be present in only skeletal form.) In the example above, the team might split "Simple query" and "Printing," and find a way to fit super-simple versions of each into the first iteration. The first iteration provides a skeleton for the rest of the implementation, and it helps address high risks in the project. The team is free to completely change the structure around later, but the first iteration provides a starting point. Other IterationsUse however many story points the team finished in the last iteration as the estimate for how many points will be done in the next iteration. (This is called the "Yesterday’s Weather" rule: the best predictor for today’s weather was yesterday’s weather.) For example:
The velocity may bounce around some at first, but it usually stabilizes. Notice that in the release plan we originally expected to get 120 points in 3 iterations, but we only completed 100 points worth. And at the end of the first iteration, it looked even bleaker. This is a place where the customer’s involvement is crucial: the customer can split or simplify stories, move the end date, ask for more people, cancel the project, or do whatever they need to do given the status of the project. How does a team increase its velocity? If a team feels they're on track to finish early, they'll ask for more work in the middle of the iteration. Iteration PlanningGoing a level deeper, XP uses a similar process for deciding what to do in an iteration.
The tasks for an iteration are in the development team's purview. It's typical for the customer to be present during this planning, as there will often be questions. These are the two most common approaches to task estimation:
The iteration planning is usually done the first morning of an iteration. The iteration plan will often change during an iteration as a team learns about tasks they missed, or come up with a better or different way to do things. What's Interesting About XP's Planning Processes?
Resources
[Written Nov. 5, 2001. Updated Feb. 27, 2002 due to feedback from Kurt Keutzer and Ivan Tomek. Minor revisions May 27, 2006.] |
|