The XP Programmer's Cube is an artifact that captures the key activities
in a day in the life of an XP programmer. |
XP Programming Activities
XP is unusual as methodologies go, in that it prescribes activities at
the day-by-day (and even at the minute-by-minute) level.
A state machine is a traditional way to show a set of activities and
the possible transitions between them. We might show XP's programming activities
like this:

The triangle in the middle catches a key idea in XP:
test, then code, then refactor
This is the opposite of traditional programming:
design, then code, then test
Let's look at the activities one at a time:
Standup Meeting at 9 AM
-
This is not an official part of XP.
-
Many teams use it to get focused for the day.
-
The fixed starting time helps remind the team to work a 40-hour week.
Pair Up
-
All production code is produced by a pair.
-
The typist thinks tactically, the partner thinks strategically.
-
Switch roles periodically.
Test
-
Write only small bits of unit test code at a time.
-
Verify that the test fails before coding. (It's sure interesting if it
doesn't fail.)
-
"Test everything that could possibly break."
Code
-
"Do the Simplest Thing That Could Possibly Work."
-
Implement just enough to make the test pass.
-
Follow the team's coding standard.
Refactor
-
Seek out "code smells" (places that don't feel right); apply a refactoring;
verify that the unit tests still pass.
-
The code should:
-
Run all unit tests
-
Communicate what it needs to
-
Have no duplicate logic
-
Have as few classes and methods as possible
-
Take small steps, and unit-test after each.
-
See Refactoring, by Martin Fowler.
Q&A
-
The customer is available on-site to provide immediate answers.
-
Many questions require decisions (not facts) - and the customer should
be prepared to make them.
-
The customer should write an acceptance test or (more rarely) a story
to capture their answer.
Integrate or Toss
-
Move the code to the integration machine, build the system, and run all
tests.
-
Fix things to bring the unit tests back to 100%.
-
If you can't easily integrate, throw it away and try again tomorrow.
Return to "Pair Up"
-
If you have time left in the day, you can pair up (or at least switch roles),
and start over on another task.
Go Home @ 5PM
-
Going home on time reinforces the practice of having a 40-hour week.
-
Notice that nothing is hanging over your head - everything you've done
for the day is integrated (or tossed).
The XP Programmer's Cube
By a lucky twist (and a little fiddling), it turns out that the core of
this cycle can be embedded onto the shape of a cube:

It's unlikely that a real team will follow the process by sitting down
and flipping the cube every time they make a move - so why bother?
-
A 3-dimensional artifact can't be left under a pile of paper - it has a
better chance of being looked at.
-
The cube can help in training, giving beginners something concrete to
look at and think about.
-
The cube helps remind you of important aspects of XP:
-
Always have a partner.
-
Get answers before you code.
-
Test-first programming.
-
Throw it away when you need to.
-
Go home "clean".
Conclusion
The XP Programmer's Cube embodies the daily activities of the XP lifecycle:
Pair Up, Q&A, Test, Code, Refactor, and Integrate
or Toss
The cube is a visible artifact that can remind us of important practices
that an XP team values.
Link: Word document with a cutout cube.
NOTE: I'm still giving away pre-made cubes. Send me your physical address and
I'll send you one. Resources and Related Articles
[Written 5-31-2000; fixed typo 6-5-00.]
|